| Activity |
Period |
More information |
| Site survey for the Hornsund (HSP) broadband (BB) sensor installation |
15 - 18 June 2007 |
Report |
| Installation of the 12 DEPAS OBSs |
14-28 September 2007 |
|
| Installation of the STS-2 sensor at HSP |
14- 28 September 2007 |
|
| Installation of the STS-2 sensor on Hopen |
2nd half of September 2007 |
|
| Installation of the BB array on Bear Island (BJO) |
May/June 2008 |
|
| Two refraction/reflection line experiments with ~15 short period (SP) OBSs |
August/September 2008 |
|
| On-shore recording of the profiling experiment with ~50 SP land stations along the coast of BJO |
August/September 2008 |
|
| Demobilisation of the BB array on BJO |
Late September 2008 |
|
| Demobilisation of the 12 DEPAS OBSs |
Late September 2008 |
|
 |
|
|
|