Activity Period More information
Site survey for the Hornsund (HSP) broadband (BB) sensor installation 15 - 18 June 2007 Report
Installation of the 12 DEPAS OBSs 14-28 September 2007
Installation of the STS-2 sensor at HSP 14- 28 September 2007
Installation of the STS-2 sensor on Hopen 2nd half of September 2007
Installation of the BB array on Bear Island (BJO) May/June 2008
Two refraction/reflection line experiments with ~15 short period (SP) OBSs August/September 2008
On-shore recording of the profiling experiment with ~50 SP land stations along the coast of BJO August/September 2008
Demobilisation of the BB array on BJO Late September 2008
Demobilisation of the 12 DEPAS OBSs Late September 2008
Print
 
NORSAR | Gunnar Randers vei 15 | PO Box 53 | 2027 Kjeller, Norway | Tel: +47 63 80 59 00 | Fax +47 63 81 87 19 Developed By Assist2net.no
Home | Projects | Research | Innovation | About NORSAR | Contact
© Copyright 2012 NORSAR
Send Mail Search Search Send Mail Send Mail